Addendum No. 1: Deadline Extension for Unit-4 Rehabilitation and BOP Systems – Fincha Hydroelectric Power Plant

Addendum No. 1: Deadline Extension for Unit-4 Rehabilitation and BOP Systems – Fincha Hydroelectric Power Plant

This Addendum No. 1 for the Fincha Hydroelectric Power Plant Unit 4 procurement (Ref. No. EEP/FP1/ICB/01/2025) issues a formal time extension for several key project milestones.

Key Deadline Changes

The addendum modifies the original bidding document issued on December 07, 2025:

  • Bid Submission & Opening: The deadline has been extended by two weeks from January 21, 2026, to February 5, 2026 (Submission at 2:00 PM; Opening at 2:01 PM).
  • Pre-Bid Meeting: Rescheduled from January 1, 2026, to January 16, 2026, at 9:30 AM.
  • Site Visit: Rescheduled to take place from January 12–13, 2026.
  • Site Visit Confirmation: Bidders must now confirm participation and provide representative details by January 8, 2026.

Read Details Below